Halfway through the construction of the S61 expressway at Wysokie - Raczki section

News date: August 25, 2020
Halfway through the construction of the S61 expressway at Wysokie - Raczki section

The progress of works on the S61 expressway at Wysokie - Raczki section is currently at about 50%. Budimex is the general contractor for this project.

 

The works are several months ahead of schedule. Ground works are already completed in 90%. Work on the surface structure is already underway. A 2 km long concrete test section is already being examined. Asphalt works on cross roads are also underway. Construction of engineering structures – viaducts and crossings is advanced in 40%. Every day about 170 units of equipment are in operation on the construction site, with about 470 people.

 

The planned completion date for the entire 20-kilometre section is June 2021. Design and build works started in July 2018. The original value of the project is PLN 393 million net.