Comment on the information on the environmental decision for S19 Białystok Zachód – Ploski

News date: December 8, 2022
Comment on the information on the environmental decision for S19 Białystok Zachód – Ploski

The Management Board of Budimex S.A., with regard to Stock Exchange Report No. 72/2022, explains that as a result of decisions of court authorities (the Voivodship Administrative Court in Warsaw), independent of the contractor and the investor, the decision on environmental conditions issued on 4 June 2021 by the General Director of Environmental Protection and the preceding decision of the Regional Director of Environmental Protection in Białystok for the project and construction of the S19 expressway between Białystok Zachód and Ploski was revoked. The Budimex – Białystok Zachód – Księżyno contract was implemented based on this decision.

 

This decision also applies to sections designed in the Design & Build system by two other general contractors of the S19 route and is not related to design work.

 

The cause of withdrawal from the contract is neither attributable to Budimex S.A nor to the investor, the General Directorate for National Roads and Motorways. The design work carried out by Budimex on the basis of the existing environmental decision has been completed and can be used for further work after obtaining a new environmental decision. We are in constant contact with the General Directorate for National Roads and Motorways to work out solutions aimed at obtaining a new environmental decision as soon as possible.